spätester Anfanglate start date (The last possible date a task could be started if all predecessor and successor tasks also start and finish on their late start and late finish dates)
spätestes Endelate finish date (The latest date that a task can finish without delaying the finish of the project. It is based on the task's late start date, as well as the late start and late finish dates of predecessor and successor tasks, and other constraints)