actual cost of work performed | coût réel du travail effectué (The actual costs incurred for work already performed by a resource on a task, up to the project status date or today's date) |
budgeted cost of work performed | Coût Budgétisé du Travail Effectué (The earned value field that indicates how much of the task's budget should have been spent, given the actual duration of the task) |
budgeted cost of work scheduled | Coût Budgétisé du Travail Prévu (The earned value field that shows how much of the budget should have been spent, in view of the baseline cost of the task, assignment, or resource. BCWS is calculated as the cumulative timephased baseline costs up to the status date or today's date) |
capitalization of cost | capitalisation des coûts (The temporary treatment of the costs of hours, items, and expenses as capital until the revenue is posted) |
cost of goods sold | coût des marchandises vendues (An accounting category used to sum the financial consequences of manufacturing products and carrying inventory) |