DictionaryForumContacts

   English
Terms for subject Microsoft containing Completion | all forms
EnglishDanish
budget at completionbudget ved afslutning (The original project, resource, and assignment cost as shown in the baseline plan. The baseline cost is a snapshot of the cost at the time when the baseline plan was saved)
estimate at completionestimat ved fuldførelse (The expected total cost of a task or project, based on performance as of the status date. EAC is calculated as follows: EAC = ACWP + (BAC-BCWP)/CPI)
estimate at completionvurdering ved afslutning (The expected total cost of a task or project, based on performance as of the status date. EAC is calculated as follows: EAC = ACWP + (BAC-BCWP)/CPI)
variance at completionafvigelse ved afslutning (The earned value field that shows the difference between the budget at completion [BAC] and the estimate at completion [EAC]. In Project, the EAC is the Total Cost field, and the BAC is the Baseline Cost field)